Real work allocation

More
07 May 2013 10:07 #1 by Nic
Real work allocation was created by Nic
Hello everyboby, I did a search but I did not find a topic releated to my issue.
Ok, I need to know if there is an option that "automaticaly" keep trace of the work made by resurces.
Exe: I have a miller, he works 8 hours per day. The project he works on last 16 hours. I would like not to update every single day if he has worked on the project but just if the work was done after 16hours. In the same time I would like to see the progress bar of the work constantily updated by the system ,basically after 8 hours the system should say that the project is 50% complete.

I hope to have been clear.

Thanks a lot

Please Log in or Create an account to join the conversation.

More
07 May 2013 12:05 #2 by babynus
Replied by babynus on topic Re: Real work allocation

I need to know if there is an option that "automaticaly" keep trace of the work made by resurces.

Not a trace like history on items, but you can check real work input on screen "real work allocation" and validate work for a given week (this will fix work)

The project he works on last 16 hours

A Project 2 days long : very very small project indeed :blink: . Better manage it as an activity... :whistle:

I would like not to update every single day if he has worked on the project but just if the work was done after 16hours

Just check the project progress.

In the same time I would like to see the progress bar of the work constantily updated by the system

Just have a look at Gantt planning view ;)

basically after 8 hours the system should say that the project is 50% complete.

It does : it is just called progress :whistle:
But of course, the resource must enter his real work in the tool, and possibly re-evaluate left work : the tool will not guess and read on one's mind :evil:

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
30 Sep 2013 09:53 - 30 Sep 2013 09:54 #3 by climb4fun
Replied by climb4fun on topic Re: Real work allocation
Hi,

basically after 8 hours the system should say that the project is 50% complete


may be an important hint for you:

There are two "progress" values:
1. progress = real work / planned work * 100
2. exepected = real work / valided work * 100

Difference is, one is planned progress and validated is progress on approved work/budget.

Regards,

Klaus
Last edit: 30 Sep 2013 09:54 by climb4fun.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.