Activied planned for Mon&Tue just 4hours per day during 5 weeks - How can I create it ?

More
08 Jul 2013 16:51 #1 by ccattani
How can I create an activity planned to be delivered just during 4 hours on modays and tuesdays during 5 weeks ?

Regards

Carlos

Please Log in or Create an account to join the conversation.

More
08 Jul 2013 17:12 #2 by babynus
Hi,

There is no planning mode that will ensure this so specific planning.
Maybe with a planning mode 'regular in half days', for a task with 40 hours assigned, you'll get something apprimatively fitting.
The best way to get exactly what you expect is to directly enter the real work in the real work allocation screen for this task.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
16 Jul 2013 18:32 #3 by ccattani
I have a 3 days duration activity which in regular planning (as soon as possible) is planned correctly (3 days), but when I change the planning to Regular in Half Days, it remains with a 3 days duration instead of 6. I'm attaching the activity'ws configuration screen.

Attachments:

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.048 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.