I'm approving a weeks work in the Real Work Allocation Screen, but it never appears to the project leader for validation.
I have set in the project definition screen the manager field to the Project Manager user and have also included him in the project's affectation list but with no rate for this project (the rate field is left blank).
How must the project and/or activity must be configuren in order for the project leader to be able to check and approve this ?
Validation rights has no matter with Project Manager.
The validation right depends on user profile.
You just have to correctly parameter the profiles who may validate work in the "specific access mode" screen.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.