Is it possible to move all dates (of activities,..) just by moving the dates of PROJECT?

More
23 Sep 2013 11:44 #1 by lutror
I've copied a project with these activities and programming (dates). Is it possible to move all dates (of activities, milestones ..) automatically, just by moving the dates of the PROJECT?

Please Log in or Create an account to join the conversation.

More
24 Sep 2013 10:33 #2 by babynus
No, not possible for "requested" and "validated" dates.
For planned date : a new planning calculation should do the job.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: lutror

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.037 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.