18 Oct 2013 15:27 #1 by sanae
Validated work was created by sanae
why is the validates work is not directly calculated by the sum of validated activity work, just as the assigned work?
is there a way to make is calculated automatically ?

Please Log in or Create an account to join the conversation.

More
18 Oct 2013 16:34 #2 by babynus
Replied by babynus on topic Validated work
Because in most cases, validated work is defined only on top level (for instance for project, or phase activities). Systematic sum would erase these values...
An evolution is planned to let the choice on sum or not (Ticket #486)

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: sanae

Please Log in or Create an account to join the conversation.

More
21 Oct 2013 10:51 #3 by climb4fun
Replied by climb4fun on topic Validated work
Hi all,

in our perimeter we use validated work as "approved" effort / work for the activities. Hence this value will be entered on a decision, not on a calculation. For us the current implementation is perfect.

In the report "Work synthesis per activity" the summary is not calculated. Here it would be appreciated, when it will be the sum out of all activities related to the project.

Regards,

Klaus
The following user(s) said Thank You: sanae

Please Log in or Create an account to join the conversation.

More
21 Oct 2013 11:26 #4 by babynus
Replied by babynus on topic Validated work
Hi Klaus,

Note added to ticekt #486
;)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
21 Oct 2013 12:50 #5 by sanae
Replied by sanae on topic Validated work
Still, the program compare the validated work with the assigned work for every activity and sub activity !! so the values should be the same and in this case making both the fields automatically calculated should have been the right thing to do
don't u think ?

Please Log in or Create an account to join the conversation.

More
21 Oct 2013 14:34 #6 by babynus
Replied by babynus on topic Validated work
That is why evolution is planned to set it possible...

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.041 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.