If I have two projects of same priority (say, 500), is it possible to use Activities priority to plan some activities of Project2 before some activities of Project2 ?
Let's say I have:
*P1 (prio = 500)
- A1 (prio = 400)
- A2 (prio = 500)
*P2 (prio = 500)
- A3 (prio = 400)
- A4 (prio = 500)
All these activities are planned ASAP.
I would expect to have planned in order:
- A1 (lowest priority, lowest WBS)
- A3 (lowest priority)
- A2
- A4
However I seem to be getting A1, A2, A3, A4. Is it that the WBS of the project takes precedence over the priority of the activites ? (i.e. it seems that all activities of P1 are planned before activities of P2).
Yes indeed, I had "RTFM"
I was just wondering if the fact that priority comes before wbs is valid both for projects priority and activities priority, mixed together.
Thanks for the confirmation, I guess I must have some other dependency which I missed!
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.