I have an activity that has 2 assignments and one of the assignments (resource) has now left, the activity is complete even though it didn't take as much time as planned.
But it will not left me close this activity as there is "left work" - I have no idea how to close this - please see attached for the situation.
babynus wrote: Just edit the assignment and set left work to 0.
This can also be done throught the '"real work allocation" screen.
Then you can close the activity.
That is great - thanks - it worked in that case. NOw I have another case - but there are no assignments this time. Is there another advice you could favor me with please?
The picture is clear : you still have some left work (1 hour).
If you don't have an assignment on the activity, then possibly left work is on a daughter activity (activity with parent activity as current activity).
A glance at the planning view will help you see the hierarchic links.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.