22 Feb 2014 16:51 #1 by barrys
I have an activity that has 2 assignments and one of the assignments (resource) has now left, the activity is complete even though it didn't take as much time as planned.

But it will not left me close this activity as there is "left work" - I have no idea how to close this - please see attached for the situation.
Attachments:

Please Log in or Create an account to join the conversation.

More
22 Feb 2014 17:35 #2 by babynus
Just edit the assignment and set left work to 0.
This can also be done throught the '"real work allocation" screen.

Then you can close the activity.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
22 Feb 2014 21:47 #3 by barrys

babynus wrote: Just edit the assignment and set left work to 0.
This can also be done throught the '"real work allocation" screen.

Then you can close the activity.


That is great - thanks - it worked in that case. NOw I have another case - but there are no assignments this time. Is there another advice you could favor me with please?

Please Log in or Create an account to join the conversation.

More
23 Feb 2014 00:01 #4 by babynus
I would need more detail.

What is the message ?

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
23 Feb 2014 10:58 #5 by barrys

babynus wrote: I would need more detail.

What is the message ?


Here is another picture and the message is the same... "Unable to close an element with left work"
Attachments:

Please Log in or Create an account to join the conversation.

More
23 Feb 2014 12:20 #6 by babynus
The picture is clear : you still have some left work (1 hour).
If you don't have an assignment on the activity, then possibly left work is on a daughter activity (activity with parent activity as current activity).
A glance at the planning view will help you see the hierarchic links.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.058 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.