We've been advised, that we shouldn't create a project for everything, if a job is too small to perhaps warrant such a configuration.
So if an Activity is maybe 1-2 days, it could be an activity of a project called "Mini projects".
The issue I'm seeing here, is if I plan 1 of the "Activities" in this project... there is no way to finalise this? The next time I add a small activity to be planned, it may well affect the other activity i've planned/agreed with the client?
We've been advised, that we shouldn't create a project for everything, if a job is too small to perhaps warrant such a configuration.
I confirm
So if an Activity is maybe 1-2 days, it could be an activity of a project called "Mini projects".
Yes, good choice
The issue I'm seeing here, is if I plan 1 of the "Activities" in this project... there is no way to finalise this? The next time I add a small activity to be planned, it may well affect the other activity i've planned/agreed with the client?
If your first activity has higher priority (lower value of "priority" or just samller WBS), it will be planned before the second one. So the second one should not interact with first one.
You can also add a dependency to force the second one to start after the first one.
Activity1 is a fixed date (can't move) because for example we've arranged it with 30 people, a big meeting and simply something that CANNOT slip in terms of delivery. It's a specified time/place possibly with people around the world.
Activity2 comes in and needs to be planned "ASAP" but uses the same resources
There is no risk Activity2 might accidentally reschedule Activity1?
Activity1 is a fixed date (can't move) because for example we've arranged it with 30 people, a big meeting and simply something that CANNOT slip in terms of delivery. It's a specified time/place possibly with people around the world.
Just record it as a Meeting
Activity2 comes in and needs to be planned "ASAP" but uses the same resources
There is no risk Activity2 might accidentally reschedule Activity1?
If Activity 1 comes first (in priority and / or WBS) there is no chance that same resource will be booked first on activity 2.
Planning in ProjeQtOr is quite intuitive.
If fills availability as you would to it yourself, filleing cells in an Excel sheet, one by one, woith linear rule.
Forget all the ununderstandable planning results you could have with MS-Project
Activity1 is a fixed date (can't move) because for example we've arranged it with 30 people, a big meeting and simply something that CANNOT slip in terms of delivery. It's a specified time/place possibly with people around the world.
Just record it as a Meeting
Not possible, as it's a development task. For example code completed, so now needs to work with external company to test on a specific date/time, which may result in some more planning being required.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.