Hello is it possible to remove the access to the dates in the progress section of a task.
I understand that they have to be able to enter time in the real work section, but I don't want them to be able to manipulate
the task date(s) to their advantage like changing the due date to take a slow working day on me...

I did take a look at the access right section, but did not identify what I was looking for.

Thanks for your time.
Regards!

Please Log in or Create an account to join the conversation.

More
05 Mar 2014 18:40 #2 by babynus
Replied by babynus on topic Project Member rights
No,
there is no fine restriction on dates.

But if anyone changes some date, it is traced in the history.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.