what Babynus said is that you have to create project first.
Use PROJECT screen, then create a new project (you need only name and short description to do this, you can fill other fields later...).
When your project is created, you need to describe project team (use affectations to add ressources to project), then you can create activities and milestones (tou can only affect ressources which have been affected to project).
Use previous and next element in activities and milestone to link then, so you will get your planning.
So, according to your way to plan project, you can at choice drive your project by delay (using fixed duration mode) or charges (using by exemple as soon as possible). If you drive by delay you only need to describe duration of tasks (or start and end date), if you drive by charges, you need to describe assigned charge for each ressources you put on duty.
I apologize for my english, but, cause you're spanish, i thnik you will understand me.
I've done
Creating several projects
Creating resources
Allocation of resources to projects
Creation of actividades
Allocation of resources to activities
Allocation of activities to projects
Creating milestones
Assignment of milestones
The problem is:
I generate to planning screen and I click the "Calculate planning" button (running gears)
Selected the project in the planning screen (running gears)
I select a date
I select generate
And does nothing ........
The screen shows nothing. The screen remains the same, empty
It's clear your activity has alll needed to get some planning.
So we only have two options :
1) you're facing and issue
=> then you should retrieve an error, either in the log file or in the browser console.
=> please report any error
2) your project is in one of the cases that forbid planning
=> there are 3 cases when a project is not planned
1) the project is closed : this is noit the case as your activity is not closed, and you cannot close a project with non-closed activities
2) the type of your project is "Administrative" : administrative projects are never planned. Just change project type will solve your issue.
3) you checked "fix planning" on your project : this is a function to avoid planning of a project (when planning is correct and you want to be sure it is not changed)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.