Assigned work, real work, left work and planned work (and corresponding costs) are consolidated (summed up) on parent items, so that project sums up total work for all sub_project, activities and sub-activitie.
But up to 4.3, validated work was not.
It was designed this way because in most cases, validated work of elementary tasks is not known. Only validated work for main tasks (phases) is.
So on V4.4, you now can choose to consolidate validated work to parents.
THere is a new parameter in global parameter designed for this.
Possible values are :
- never : do not cosolidate
- only if set : will consolidate (sum) only if sub-items value is not null, so that existing value is not erased by non existing values
- always : will always consolidate from lowest items to top (so may erase some data)
Default value is 'never', to preserve existing behavior.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.