08 Oct 2014 19:35 #1 by francis2301
Hi,
I have a doubt about the expected behavior in reports related to project expenses:
- Project expense per month
- Total expense per month
- Total Expense and Cost Per Month

I've entered some project expenses, filling out the fields planned cost & date and real cost & date.

When I run the reports mentioned above, costs are shown only in "real cost" line. Planned values are not shown.
At first, I thought it was because planned costs and real cost were the same. So, I changed values to have a difference between planned costs and real costs, and still showing no costs in the "planned cost" line, in the reports. I've tried also to change the date/month of real date, so it would be different from planned date, and still, no planned values were shown in the reports.

Is this a expected behaviour?

Also, I've noticed that when the values are in millions, the graph cuts the values on the left of the graph.

Attached follows a print screen of the values shown in the report and the graph.

Thanks in advance. Kind regards.

Please Log in or Create an account to join the conversation.

More
09 Oct 2014 11:29 #2 by babynus
Hi,

This is designed behavior...
Target of these reports is to mesure total of expense, not to compare real from expected.
So for a given expense, if real is set, it is taken into account, if not then expected is taken into account.

Attached follows a print screen of the values shown in the report and the graph.

Sorry, no file attached

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
09 Oct 2014 13:56 #3 by francis2301
Sorry for forgetting the attachment :S . But, you got it perfectly :cheer:

Maybe as evolution for cost reports would be some reports for comparing planned vs real.

Thanks for your answer and clarifying my doubt.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.