Let me explain the steps and then get to my question.
Activity 1: Planned effort = 24 hours
Real work = 16 hours
% completion is 66.67%
This is the current behaviour.
However my question is, if my estimated effort is wrong and 16 hours is good enough to complete the work, is there any way for me to mark the Activity as 100% completed (I can mark the activity status as done, however my progress is still shown as 66.67%)? Or Is there any workaround to circumvent this issue?
I tried setting the left work to zero, however at activity level (which was always restricted). After your response tried it at the developer level (to whom the activity is assigned). It works like a charm.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.