Percentage completion of activity

More
14 Nov 2014 08:36 #1 by kiranlv
Hi,

Let me explain the steps and then get to my question.
Activity 1: Planned effort = 24 hours
Real work = 16 hours
% completion is 66.67%

This is the current behaviour.

However my question is, if my estimated effort is wrong and 16 hours is good enough to complete the work, is there any way for me to mark the Activity as 100% completed (I can mark the activity status as done, however my progress is still shown as 66.67%)? Or Is there any workaround to circumvent this issue?

We are using V4.2.3.

Thanks.
Kiran
The topic has been locked.
More
14 Nov 2014 10:18 - 14 Nov 2014 10:18 #2 by babynus
Just set left work to zero B)

Babynus
Administrator of ProjeQtOr web site
Last edit: 14 Nov 2014 10:18 by babynus.
The topic has been locked.
More
14 Nov 2014 11:08 #3 by kiranlv
That was quick !!!!!!

I tried setting the left work to zero, however at activity level (which was always restricted). After your response tried it at the developer level (to whom the activity is assigned). It works like a charm.

Thanks again for the quick response.
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.052 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.