Force usage of two resources for a task

More
23 Jan 2015 13:42 #1 by greengolfer
Hello,
I am evaluation Projeqtor for my company and it is really a fantastic tool!!
So far, I have been able to do almost exactly what I wanted.
I have a question though.
I would like to know if it is possible and how to create task that needs eg a Machine (physical resource) and a human to complete.
I have created a tool (say hammer) and a person say Joe. In order to complete a task "putting nails" I need both the hammer and Joe.
If Joe is unavailable on Friday, I can't use the hammer to work on the task that day.

Or if the hammer is used on another task by jane, Joe can't work...

Is there a way to do that?
Thanks,

RG

Please Log in or Create an account to join the conversation.

More
23 Jan 2015 14:05 #2 by babynus
Hi,

To do what you describe is easy, and you're almost there :
- Create one resource for Hammer
- Create one resource for Joe
- Assign Hammer and Joe to same task (with same work)
- change planning mode of the task to "work together" :woohoo:
Run planning calculation... ;)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.027 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.