26 Jan 2015 17:34 #1 by Zeby
Hello,

this is what I try to do: use ProjeQtOr to manage multiple projects simultaneously.

I wish I could put my resources, every week, 2 days on a project and two days on another project.

I tried with 4.5.4 version, but I have not succeeded ...

So my question is this: is it possible to choose a calendar by project ?
So I can say that on Monday/Tuesday is always a holiday for a project and Wednesday/Thursday for another... With an automatic calculation of schedules.

thank you in advance for your answers and good evening ...

Please Log in or Create an account to join the conversation.

More
27 Jan 2015 11:47 #2 by babynus

So my question is this: is it possible to choose a calendar by project ?

No calendars are defined for resources.

But you can get result you wish :
- set affectation rate to 40% on both projects (40% is 2 days on a 5 days week)
- define priority of project working on Monday & Tuesday with priority number lower (higher priority as 1 is highest priority) than other project
Run planning calculation

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.027 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.