05 Mar 2015 10:59 #1 by c.pache
Hi !
I have a question : when I use as soon as possible planning mode, planning calculation don't take care about validated start date. Is it an issue ?
Thanx for your answer.
Cédric

Please Log in or Create an account to join the conversation.

More
05 Mar 2015 18:38 #2 by babynus

when I use as soon as possible planning mode, planning calculation don't take care about validated start date. Is it an issue ?

No it is not an issue, it is expected behavior.
Validated start and end dates are records for initial planning, on which you have committed.
If you want to fix start date you have to add fix milestone and add dependency to activity.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
06 Mar 2015 08:54 #3 by c.pache
Thank you for your answer, I'll use Milestone !

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.024 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.