I am fairly new to projeqtor and cannot assign an activity price. It is not showing up in the activity description like it shows on the online manual. I created a priced activity in the Financials/Activity Prices but how do assign it to an activity?
Activity price in Financial menu is only ffor Billing purpose.
The way it works is :
- you define activity price for a project and activity type.
- you generate a Bill, for an activity price, a resource and a period (start and end dates).
- the program generates the Billed amount from work days for resource during the period on activities given for activity type, multiplicated by activity price.
This will never be shown on he activity, only on the bill.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.