MS Project Behavior

More
10 Jun 2015 08:47 #1 by Iaurkano
MS Project Behavior was created by Iaurkano
Hi babynus,

one question, is it possible when there is no assignation on task that pojeqtor had the same behavior than MS Project.

this mean to day projeqtor behavior is : when i have a task with duration but no date nor assignation wich is linked with another task the first one is not planned. no bar in gantt chart. In project the task duration is shown and the constraint ( the link to the precious or next task) is taken into account to fix the start and end date.

i don"t know if im clear ?!!!!

thank's for all.

Please Log in or Create an account to join the conversation.

More
10 Jun 2015 09:22 #2 by babynus
Replied by babynus on topic MS Project Behavior
There are some kind of improvements this way in V5.0, except that duration is taken into account only if planning mode is "fixed duration".
Your proposale is interesting. I'll have a look to see if this can be completed before V5.0 deployment.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.026 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.