In my report "project dashboard", the validated work of the activity is always at 0, however the validated work of the project is correct(see attachment file "report").
I have correctly fill in the validated work of each activity and the the validated work is automatically consolidated to the project (see attachment file "activity").
Why the validated work of the activity isn't displayed in the board ?
I have a clue :
In this report, tasks summary is based on Assigned Work (table assignment) which does not include validated work.
Moreover, on this report, the smiley for the tasks is based on real+left conpared to assigned...
I think this was done to be able to summarize values per type of activity, what is not possible if you work directly on tasks as you would sum-up values for parent tasks as well as elementary tasks.
So, better leave the report like this, without validated work for tasks.
I just change display to hide title and remove the zero value.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.