I have a very small project that lasts for a week with 3 resources. Due to resource crunch i've asked the two resources to stretch the working hours (more than 8 hours) and complete the task in one week itself.
But though i set "Fixed dates" mode and assigned resource with days (7.5/week), after "Calculate activities planning" the dates are shifting to adjust 8 hours / day and the Project's planning dates are moving to 1.5 weeks. I don't want to change working hours >8, because it impacts other projects too.
Is there any workaround for this?
Thanks
Raj
Last edit: 05 Aug 2015 17:54 by oracleraj. Reason: symbol
A workaround is to increase resource capacity.
(as it is exactly what you request)
But take care as this will be applied to all projects of the resources.
Another workaround (my prefered) can be to consider that left work is just 5 day (even is assigned work is more).
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.