ProjeQtOr free project management software - Task status is not getting changed to 100% when task is completed with less than estimated effort - ProjeQtOr
 
 

Task status is not getting changed to 100% when task is completed with less than estimated effort

More
07 Aug 2015 12:33 #1 by gv
1. Task is created with 12 hours estimated effort
2. Task is completed with effort of 10 hours
3. User entered 10 hours for that task and changed the status to done.
4. But in Gantt chart it is showing status completed as 83% not 100%.

Is there some thing we are missing in configuration to set as tasks completed 100%?

Please Log in or Create an account to join the conversation.

More
07 Aug 2015 13:48 #2 by babynus
Status to done is not enough to define that there is not left work.
In many cases, after work is done, responsible is changed to get a validation, that may lead to work input.

So to define that there is no left work ... you must set left work to zero :silly:
This should be done be resource in Real Work Allocation screen, or can be fixed by project leader on activity assignement.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.036 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.