ProjeQtOr free project management software - Task status is not getting changed to 100% when task is completed with less than estimated effort - ProjeQtOr
1. Task is created with 12 hours estimated effort
2. Task is completed with effort of 10 hours
3. User entered 10 hours for that task and changed the status to done.
4. But in Gantt chart it is showing status completed as 83% not 100%.
Is there some thing we are missing in configuration to set as tasks completed 100%?
Status to done is not enough to define that there is not left work.
In many cases, after work is done, responsible is changed to get a validation, that may lead to work input.
So to define that there is no left work ... you must set left work to zero
This should be done be resource in Real Work Allocation screen, or can be fixed by project leader on activity assignement.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.