View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Support us on Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - How is affectation rate handled? - ProjeQtOr
 

How is affectation rate handled?

More
09 Sep 2015 17:55 - 09 Sep 2015 19:32 #1 by soyelsimo
Hi there!!

Im trying to understand how the affectation rate works. Right now I leave it at 100% and doesn't seems to be logic.

To match the productivity with the affetaction rate I was wonder in what time frame is based.

I have activity type A that I can do 2 per week, and activity B I can do 4 per week.
Weekly basis affectation for type A is 50% and for type B is 25%
Monthly basis (lets say 4 weeks) (8 activities) type A = 12.5% (1/8th) and (16 activities) type B = 6,25% (1/16th)
Or in yearly basis (52 weeks) type A = 0,96% (1/104th) and type B = 0,48% (1/208th)

So in what time frame I'll need to measure productivity to be related with affectation rate?
and would make sense, add a resources to a project with none rate and set the rate in subactivities where the resource is used?
Thank you!!
Last edit: 09 Sep 2015 19:32 by soyelsimo.

Please Log in or Create an account to join the conversation.

More
09 Sep 2015 19:30 #2 by babynus

Im trying to understand how the affectation rate works.

It works fine thank you :evil:

Right now I leave it at 100%

IT is default, and works fine in many cases.

and doesn't seems to be logic.

all depends what you expect

To match the productivity with the affetaction rate I was wonder in what time frame is based.

It is based on a daily bases.
Once again RTFM : hit F1 on Activity page, move 2 pages up to get to page 3/5 of activity, whare assignment is explained.

I have activity type A that I can do 2 per week, and activity B I can do 4 per week.

2 what, 4 what.
Number of activities ?
If you have activity A, it means you'll work on this activity, not run several times activities of this kind...

Weekly basis affectation for type A is 50% and for type B is 25%

This means (to explain) thant you can work 0,5 days per day on A and 0,25 days per day on B (respectively 4 hours and 2 hours for 8 hours day).

Monthly basis (lets say 4 weeks) (8 activities) type A = 12.5% (1/8th) and (16 activities) type B = 6,25% (1/16th)
Or in yearly basis (52 weeks) type A = 0,96% (1/104th) and type B = 0,48% (1/208th)

You lost me there :(
I'm afraid you have a unit issue : projeqtor is Work driven PM tool, so you have to deal with "how many days (or hours) I'll work on this activity"

So in what time frame I'll need to measure productivity to be related with affectation rate?

In days (or hours dependeing of global parametering)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
09 Sep 2015 20:13 #3 by soyelsimo
well, I see I have an issue with the concept itself :side:

with this I got it.

This means (to explain) thant you can work 0,5 days per day on A and 0,25 days per day on B (respectively 4 hours and 2 hours for 8 hours day).


I will measure it in hours and assign % based on weekly hours, that suits best for me. Has this affectation impact on the planning calculation?
and would make sense, add a resources to a project with none rate and set the rate on the subactivities where the resource is used?

Thanks a lot!!

Please Log in or Create an account to join the conversation.

More
09 Sep 2015 20:37 #4 by babynus

Has this affectation impact on the planning calculation?

Of course, if is done for that.

and would make sense, add a resources to a project with none rate and set the rate on the subactivities where the resource is used?

No, you should not set project affectation rate to zero. This is an extra control on project : you cannot work more than rate% on a weekly basis. This mean that if you set a 50% affectation rate on a project, you cannot work more than 2,5 days (5 x 50%) per week on this project (on all the tasks of that project).

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
09 Sep 2015 22:36 #5 by soyelsimo
Ok, is sort of what i'm looking for. When I say set to none the affectation I mean leave it blank, not zero, and then set the affectation on each activity.

I'm getting lost on why or when I would set affectation on the subactivity or on the parent project or activity.

I'm interested on time control on subactivity level more than on the overall project. then would make more sense to set affectation on subactivities rather than on parent project?

Please Log in or Create an account to join the conversation.

More
10 Sep 2015 13:39 #6 by babynus
You must define affectation to project :
- to give the resource access to elements of the project
- to be able to select resource in assignment definition
Affectation rate limits planning calculation on weekly basis
([Resource capacity] x [affectation rate] x 5 days per week on the project max)

You must define assignement to activity :
- to plan the work on the activity
- so that resource can enter real work on activity
Assignment rate limits planning calculation on daily basis
([Resource capacity] x [assignment rate] x 1 days per day on the activity max)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.038 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.