I'm not sure if this is an issue or a feature, but in my case it seems like an issue. The following is applicable for V5.0.5:
I create a meeting with let's say a length of 1 hour. After that I add attendees and they receive automatically Assigned(h): 1 and Left(h): 1.
If I then adjust the length of the meeting (make it 2 hours), the field Assigned(h) and Left(h) of attendees remains with original 1h, whil I need it to become 2h. The only way to adjust the is to remove the attendees and add them again.
Is this a normal behaviour?
Yes it is expected behavior : when you create the assignment of attendees, work is proposed from meeting duration.
But it is only a proposale. You can change the value if you please.
SO there is no reason to report change of duration to assigned work as it may be expected result.
Note that you don't have to delete assignment of attendees, you can just update it.
Also note that the assigned work for meeting is only for planning : real work may always be different...
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.