I am using version 5.0.5.
When I create a project, a task for this project and that I assign resources to this task, the resource availability is not modified accordingly.
The resource appears always as available.
This is only when I start entering actual work that availability is changed. Again update is only for actual effort entered and not for the planned effort?
You must run project calculation (button on planning view) to book resource availability.
(in projeqtor, planning calculation is not automatic : it is considered as managerment act)
Thanks for your answer.
Actually my issue came from the fact that I ticked "fix planning" on the project.
Therefore, even when I ran "project calculation", the resource's plannings were not updated.
Now I understand. Initially I thought that this option would fix the dates and force to add resource to reach effort budgeted.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.