Because you just defined the Validated work, which is just a reference (informative data to define margin, no effect on planning)
You have to add work through "assignment" (list with "add" button)
Notice that projector plan "left work" : you have no left work ,so nothing is planned.
Just to be sure, I assigned the work with the "change button" (pen) directly on the activity details on the Assignement tab, is it the best practise or it exists a better practise?
it is the best practice for the Project Leader.
(well, in fact you should define assigned and left work while Creating the assignment).
What is important, it is that each project member will re-evaluate left work reguliarly (at least once a week) and update it in the Real Work Allocation (imputations) screen.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.