Shouldn't it be planned after? That is the reason why one activity or project is set predecessor of other, isn't it?
As well I set priorities:
TRA-NSW 101 to 500
DUB-NSW 101 to 600
PRO-NSW 101 to 600
MIX-NSW 101 to 700
TRA is first and mandatory to begind DUB and PRO. PRO will start before DUB and go parallel to DUB, these are mandatory to start MIX. So MIX will never be able to start before any of the other activities.
How can I make to be planned In the correct order?
Is priority global? or is it taken in to count inside the parent project?
1) Did you run planning calculation ?
2) Check MIX-NSW 101 : if planning mode is "As soon as possible" and no planned work, task is not really planned. No work should only be applied to "fixed duration" tasks.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.