What's reassessed work ? and how it's calculed
Some times when i calcule planning for an activitity witch valitdated for example on 21/10/2015 to 21/810/2015 (1 day), the system calculate others planned dates , for example form 22/10/2015 to 02/11/2015 !!
PS: my planning parameter is :" Fixed duration"
Reassessed = real + left,
it is re-evaluated work from real input and re-evaluation of left work.
Some times when i calcule planning for an activitity witch valitdated for example on 21/10/2015 to 21/810/2015 (1 day), the system calculate others planned dates , for example form 22/10/2015 to 02/11/2015 !!
If you enter some work, left work is planned depending on resource avalability.
PS: my planning parameter is :" Fixed duration"
If you choose "fixed duration", you should not define work (no assignment), otherwise, task is planned "regulliarly" for the duration.
Can i entry manually a planned date ?
No, because they are planned : you don't plan. ProjeQtOr does.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.