babynus wrote: no !
First a year is not 365 days (in a workly basis) but about 220 (must exclude week-ends, off days, holidays).
Then if eauc is 35% on the task, then each has 220 * 0.35 = 77 days on the task
And total assigned work on the task is 77 * 7 = 537 days.
(this is not Prject Management, just arythmetics)
Just to be sure again , you assign 77 days on the task with 100% on project assigment and 100% on activity task, could you confirm me?
I'm not agree with you but just to be more clear, ressources have another projects to do every day.
33% Project 1 ---> "regular between dates" ---> cyclic tasks
33% Projet 2 ---> "reguler between dates" ---> cyclic tasks
33% Projet in general ---> ASAP
In ProjeQtOr, with project assigment at 100% and activity assigment at 33%, I have 2.5h every day for this task during the period and this is what I expect.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.