We would like to foresee if too many resources are taking their Christmas holidays at the same time so we created an administrative with a "days off" activity (as you suggested in another topic) and everyone input their holidays on Real Work Allocation.
Unfortunately, when we select the project Administrative on top left of the application, and we go to Resource planning screen, I have the message "No data to display". Were these activities hidden on purpose? How can I disable that?
Administrative projects are not displayed in Gant chart.
It is designed this way : administrative project are not "planned"
Resource planning would not halp you for what you expect : you would just see a bar from first day out to last day out, even if resouce is working in between.
Use reports for what you expect.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.