I explain my doubt; I have one cyclic task (planification = regular between two dates) (70% of a day time) and the other 30% are dedicated to all projects.
For example, for one ressource, I have 4 projects. So, how can I assign the 30% for these 4 projects?
My solutions are:
- 30% / 4 = 7.5% ressource affected on each project (problem: what's happen if today, I have 6 projects, I need to update all my affectations?)
- 30% on all activities ???
My two solutions are not optimal, do you have a better solution?
Regular between dates will be planned first (it is one of the priority rules for planning) and other projects will only use left availability, so affectation rate at 100% will use the 30% left.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.