Hello. We need a help.
We work on big projects and often several scope of work go to other company (subcontractor). Sometimes we work on full project.
Subcontractor haven't access to our Projeqtor and it isn't needed.
If we give work to other company, we want plan this work (and it's progress). But only we know is start and end dates and price of work.
(Also this external work has dependencies with our outer work).
Any idea how correctly plan in this situation?
Is it possible in currrent release or need more functionality?
Then you can either
1) define an expense to enter cost of subcontractor,
or
2) manage cost as resource cost : you define a resource for subcontractor with capacity = number of persons in subcontractor's team
and add real work corresponding to cost of subcontractor's intervention
Then you enter real work when subcontractors gives information about progress (you can enter all on one day, even if is is more than capacity)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.