[SOLVED] Regular between two dates

More
06 Jan 2016 18:28 #1 by El Wallos
Hi

I have a cyclic task which was planned with "regular between two dates" to represent a "run IT task" (near to 30% of our time each day, because we are not at 100% full project). I have xxx hrs assigned between last december to dec 2016 and I want to understand what's happen if I don't consume all my assigned work (i.e. when we come near to dec 2016 and the left work bigger that plan, so this time was plan for left day to reach last day or I will have every day the same assign time?)

Hope I was clear.

Please Log in or Create an account to join the conversation.

More
07 Jan 2016 11:17 - 07 Jan 2016 11:17 #2 by babynus
Replied by babynus on topic Regular between two dates
All the left work will be planned for the remaining period.
So if you think (and as soon as you've god an idea about it) that you won't need all the left work, change it.

Babynus
Administrator of ProjeQtOr web site
Last edit: 07 Jan 2016 11:17 by babynus.
The following user(s) said Thank You: El Wallos

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.