consolidation travail validé

More
11 Jan 2016 08:35 #1 by FOUCHER RENAUX
Bonjour
a quoi sert la fonction consolidation du travail validé?

Please Log in or Create an account to join the conversation.

More
28 Jan 2016 14:31 #2 by richard.pare
The validated work allows to define the scheduled work.
The Scheduled work allows to calculate the margin (work).

Consolidation of validated work (cost) can be useful to sum the project validated work from values specified in tasks.

Hint:

If you want an answer to your question, you must write it in English "unwritten rule".

"Your question must be of benefit to the majority" ;)

Please Log in or Create an account to join the conversation.

More
29 Jan 2016 09:40 #3 by babynus
You have 3 consolidation methods, depending on which level you with to enter validated work.

If you have
Project1
Phase1.1
Activity1.1.1
Activity 1.1.2
Phase1.2
Activity1.2.1
Activity1.2.2
You may want to define validated work only on phase level. If consolidation is automatic, 0 values on activity level would erase Phase value.

Imagine you define
validate on Project1=40
validate on Phase1.1=10
validate on Phase1.2=20

With consolidation = NEVER, you would get
Project1 =>40
Phase1.1 => 10
Activity1.1.1 => 0 (not defined)
Activity 1.1.2 => 0 (not defined)
Phase1.2 => 20
Activity1.2.1 => 0 (not defined)
Activity1.2.2 => 0 (not defined)
=> Project value is not consolidated as sum of Phases

With consolidation = ALWAYS, you would get
Project1 =>0
Phase1.1 => 0
Activity1.1.1 => 0 (not defined)
Activity 1.1.2 => 0 (not defined)
Phase1.2 => 0
Activity1.2.1 => 0 (not defined)
Activity1.2.2 => 0 (not defined)
=> zero values at lowest levels are cnsolidate up to project

With consolidation = ONLY IF SET, you would get
Project1 => 30
Phase1.1 => 10
Activity1.1.1 => 0 (not defined)
Activity 1.1.2 => 0 (not defined)
Phase1.2 => 20
Activity1.2.1 => 0 (not defined)
Activity1.2.2 => 0 (not defined)
=> zero values at lowest levels do not overwrite non zero values at phase level
=> non zero values on phase level are consolidated on Project level : value is updated to sum of phases
=> This is my choice for consolidation ;)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.