Hello,
I'm testing this software, but I don't know how change the % progress of activity.
Anybody has a tutorial to help me?
I'm probably following the wrong order .
I need to know:
1 - Which fields the Project Manager need to sign in "progress" session?
2 - Which fields need to be changed to change the percentage of the activity?
ProjeQtOr is work driven.
This means that progress is calculated from work.
Work is distributed upon resource is assignments, defining Assigned Work, and Left Work (initalized to Assigned work)
Progress = Real Work / (Real Work + Left Work)
Real work is defined in Real Work allocation screen, where left work can also be updated.
You can access the online manual with [F1].
You'll find here all expected information.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.