I have two cyclic tasks (planification mode: regular between two dates) to go down the bandwith of my ressource because he is not working on project at 100% (aprox. 50%) , but sometimes I need to create a task which it takes the 100% of the bandwith, I tried to increase the % affectation (on task and project) above 100% but it is not working.
Change planning mode.
Regular between dates will regularly dispatch the assigned work during the period. So unles you define work exactly equal to suration x capacity, you won't get expected result.
I can't change it because I choose this planification mode because this ressource is not working at 100% on projects but sometimes, we have an exception that's why I asked it.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.