You answered me about priority on projects and subprojects but I did some tests and I'm not sure how to interpret the result.
My results were: (Sub= sub project, act=activities)
- If priority is medium (500) on all (project, subproject and activities), the lower WBS is planned first
- Project A (300) , Sub (500) , Act (500) and Project B (500), SUb (500) Act (300), the activity of project B is planned first, so the priority on activities is more important than priority on Project.
- Project A (300) , Sub (500) , Act (500) and Project B (500), SUb (500) Act (400), the activity of project B is planned first, I don't understand why?
Is it necesary to replan to take in charge the update of the priority even if "automatic run plan" is enabled?
Could you explain me the relation about priority between project, subproject and activities? How the priority is taken to create the planning?
Yes and no.
Automatic planning runs only on Gantt view.
If you change priority on Activity view, you have to run planning manually.
But if you do in on Gantt view, planning should be recalculated automatically.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.