[SOLVED] Cost Of Resource

More
01 Feb 2016 03:01 #1 by pavilonsxx
Cost Of Resource was created by pavilonsxx
I have a question asked people to help fo resource cost. When I create and assign initial cost for employee A is 500.000VND / d. But when that resource assigned to the activity, only 100.000nvd / d. Thanks to everyone for helping why is there this difference?
Thanks everyone.
Details with photos attached.
Attachments:

Please Log in or Create an account to join the conversation.

More
01 Feb 2016 08:32 #2 by babynus
Replied by babynus on topic Cost Of Resource
Hi,
It is because internal format for dailyCost and newDailyCost is 7,2 (five digits+2 decimals)
You currency used larger numbers.
You should increase internal format or possibly use another format for currency (1KVND=1KiloVND=1000VND)

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: pavilonsxx

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.