I would like to setup a project template that includes phases, activities, milestones, etc. with durations and links filled in. I would like to then use the template to create a new project and then just change the project start date and have all the other activities adjust the dates automatically.
I created a project with a type of template and setup all duration and linking of activities which filled-in the validated dates for each activity. When I copy it these dates come over and when I change the project start date, the activities do not update the validated or requested dates.
How do I create the template such that the dates are dependent on the project start date when copied?
The start dat that you define on Project does not condition start of project.
What should be missing is just a fixed milestone at the begining of the project that will condition the first phases/tasks.
Just change date of milestone, replan and you're in.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.