I have created a project called TSD on the Demo site. Here are the steps I took:
Create a Project of type Template with only required fields filled in
Create a Milestone to be used for project start date
Created first activity as Phase with planning as fixed duration and a duration of 10 days
Created four tasks with a parent being the Phase, planning as fixed duration and entered a number of days for the duration
Used Planning with automatic run plan checked to link the Activities and Milestone
Set the start date of the Milestone
As you can see, the start date of the Phase activity (and the project) did not move, only the end date. Also the validated duration did not change which is a requirement for a planning mode of fixed duration.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.