Is it possible to put a project in stand-by mode. The need is to free all ressource assigned on this project, when the project is intand by mode.
in fact, sometimes, we work on project plan, ressource assignement, etc. , and a change of priority happends. so the project is suspended, until an unknown date. it will done after but we dont kown when . In this case it should be great to put project in stand-by mode, to keep the plan, but it's needed that this project does not impact ressource avaibility for other one's.
You can close project affectation for these resources.
Check box "Close" in "affectation" dialog box.
You can change project affectation period.
You can fix project planning.
beszt way is to plan the project with plan start date very far inthe future (01/01/2050) for instance.
then check the fix planning ckeckbox and put in a specifc status.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.