[SOLVED] How to ling two task and thate the second begin after the end of the first

More
11 Mar 2016 11:09 - 11 Mar 2016 11:11 #1 by dnaton
Hello

Here is an example



How is it possible for two linked task to have a relation type "End to start) (The start of second can't start only after the end of the first task) ? and if it is possible, without put fixed date in the "start date validate" field

Regards,
Damien
.
ProjeQtOr v11.0.1 - Apache v2.4.56 - MariaDB v10.4.28 - PHP v8.2.4
Plugins installed : Personalized Translation 1.5 - Customization of screen 6.6
Attachments:
Last edit: 11 Mar 2016 11:11 by dnaton.

Please Log in or Create an account to join the conversation.

More
11 Mar 2016 13:53 #2 by babynus
It works how you did, but have to "re-calculate" planning.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: dnaton

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.