If I create this report as admin, I get all active projects/activities of a resource including the administrative project for the holidays.
If I do the same as project leader or project member the holidays project is missing. It would be very useful to see also this days.
Is this a bug or what am I doing wrong?
In fact, administractive projects are displayed only if Project Leader is assigned to administrative project, to get visibility on it.
But you're right, on Monthly planning report or availability reports, administrative proejcts should always be taken into account.
Ticket #2022 recorded.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.