Could You tell what smallest time could be assigned for activity? I have discovered, when time is less than 0.1 hour for activity, Projeqtor calculated wrong, it wasn't able to set dates.
Could I have ability to plan these small activity?
If you plan very small activities, maybe you should change unit for work (in global parameters) to set it ti hours.
Then you can manage fractions of hours (0,1 h).
But is it really reasonable to manage such small tasks ?
Maybe you'll spend more time managing them than treating them
IMO, tasks should not be spit to less that 1 day activitiy, and best size is about 5-10 days...
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.