I had some problems when I changed the dates to one activity in one of our projects (start and duration of validated dates).
After saving the changes ("automatic run plan" and "save dates" were che
cked), the start and finish dates were copied to planned dates, but no only to that activity, but every activity in the entire project.
I've been searching in the documentation and this forum for a "rollback" or something, but I couldn't find anything. Is there any way that I can recover my oldest dates? and why did this happened?
The project had requested dates only, with regular dependencies between activities, so I don't understand why this happened.
We are using Projeqtor 5.5.0 with MariaDB
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.