Project planning

More
21 Dec 2016 21:36 #1 by dancu
Project planning was created by dancu
I've created my project, created numerous activities with Validated Times on them... and everything was looking good.

Then I must have done something that messed it up... now all my activities in this one project have the planned start and end dates of today.. and were showing 0 hours of work left, even though there were 0 hours of real work and I had validated work for each one. It also caused my project to show 100% completed.. when it wasn't..

I went in to the Real Work Allocation screen and was able to set the left work to match how much the validated work for each activity, so that then fixed the left work and the percentage complete, but I still have the planned start and end dates set, which I think is really messing up my planning.

So the question is... how can I clear the planned start and end dates for my activities?

Also, any idea what I did so I can make sure I don't do it again?

Thanks,
Dan

Please Log in or Create an account to join the conversation.

More
26 Dec 2016 00:12 #2 by babynus
Replied by babynus on topic Project planning
Did you run planning calculation ?

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
27 Dec 2016 17:22 #3 by dancu
Replied by dancu on topic Project planning
After playing around a little more, I think that you are correct, I might have done that.

Would that explain why all my Projects/Tasks ended up with 0 hours remaining? (effectively all completed?)

Also is there a way to reset the start dates and the time remaining instead of having to go through and set the remaining hours on each item?

Please Log in or Create an account to join the conversation.

More
27 Dec 2016 18:24 #4 by babynus
Replied by babynus on topic Project planning
I think you just ommited to define some assigned work for asap tasks.
These tasks are work driven...

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.034 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.