Hello
I asked again a question about meeting's assignation.
I would like to force planning to accept that for a meeting someone could work more than the 7 hours (ETQ).
If I have a meeting with 8 hours... the assigned resource has always 1 hours not planed, because it is more that the official duration of working time for this resource (ETQ = 7 hours).
Is it possible to force it ?
Really? you can't assign for one exceptional day more that 7 hours (if ETQ = 7 hours) ? Never... Even for a meeting?
It is strange... no?
We have part-time worker... 0?8 ETQ. And all the meetings are more or less 7 hours. And the resources need to travel, and this time is for our organisation "50% working time". So for a 7 hours, the 0?8ETQ could spend 12 hours for the meeting. How could I plan a such extra times?
Don't you think it could be a good thing to make it possible in a new version?
Christophe
Really? you can't assign for one exceptional day more that 7 hours (if ETQ = 7 hours) ? Never... Even for a meeting?
No, not for resource with capacity = 1
Planning will never plan more than resource capacity.
So for a 7 hours, the 0?8ETQ could spend 12 hours for the meeting. How could I plan a such extra times?
You cannot plan this extra time on same day for the meeting.
Only possibility is to directly enter real work for the meeting : real work has not constraint and is always right.
Don't you think it could be a good thing to make it possible in a new version?
No, this is one basis on Planning calculation in ProjeQtOr...
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.