Hello, thank you for this software, just wondering how to set August 15th as holiday in the global calendar. I created a new copy of default calendar, then clicked on August 15th the color changed, and when i check the planning there is no change,
expected, the planned days advance to one extra day considering this holiday..please help
In planning view, only defaut calendar is taken into account.
If you define new calendar, you should assign it to some resources. Then on these resources, real work allocation screen will display off days for this calendar and there planning takes new calendar into account.
thanks for reply, i looking at calendar for all only not any resource specific calendar.
Also i want to use only the fp project not administrative project
1. i clicked August 14 & 15th in the calendar (default)
2. Came back to the planning view, these dates shown in grey colour.
3. but my expectation was the task to skip these days as working days
means, if a task which supposed to end by 14th should advance to 16th
kindly let me know this feature is available in fp or not
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.