You can assign several resources to same task, but be aware that with default planning mode (asap) resource may work on different days on the task. To force to have them work on same days, you must use planning mode "work together".i must skip to assign many resources on a same task ?
The function of resource on the assignment has no effect on planning, it only defined cost for the resource.i wouln't assign a developer, and a manager on an same task then.
Please Log in or Create an account to join the conversation.
Please Log in or Create an account to join the conversation.
it is possible, but possibly they will not work the same days (this is the "work together" feature)- 2) 2 resources with mode planning "as soon as possible" : in this case, it's possible that 2 resources are planned to work in the same time on this task
- 3) 2 resourc
YesQ it's ok for you ?
Difficult to analyse without steps by steps use case and all conditions identified.Q Do you know the reason ?
Please Log in or Create an account to join the conversation.
Please Log in or Create an account to join the conversation.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.