I am asking my team to put their real work and broacast the "Detailed work per resource - monthly" report.
One of our board member is asking wisely "How do we identify how good we are in forecasting ? and how do we detect underground problems?"
To illustrate: for one activity I planned "5 days" for a ressource, the "real work" entered is "12 days".
On the "Detailed work per resource - monthly" report I have no trace of the planned work.
I generated the others planning, real work and KPI reports with no success.
How can we get the synthesis, per ressource and per activity, for one month, between the "planned" work and the real "work"?
We don't have this kinfd of report "per resource".
We are designeing new report (on V6.5) to calculate resource efficiency (on tichets and activity) but not sure this will bring you the detail level you expect.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.