Once planning is calculate, a quick reverse planning is done, from end to start (taking only calculated duration of tasks), to determine latest start and end dates.
When planned dates are equal to latest dates, activity is on the critical path.
This means that if on task included in the critical path extends, whole projects extends of same duration.
but when there are none contiguous task in critical path, there is problem no ?
like when the planned end date of the first task is before the planned begin date of the next task, the critical path seem to not be display.
example in your projeqtor demo :
the task with wbs : 99.2.1 is the first task of an task chain. this task is none contiguous with the next task (wbs: 99.3.1) and it's not in critical path. but the task (wbs: 99.3.1) that is contiguous with the next step task, is in critical path.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.