View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Support us on Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] How is define the critical path in projeqtor 7.0.1 - ProjeQtOr
 
 

[SOLVED] How is define the critical path in projeqtor 7.0.1

More
30 Mar 2018 14:23 - 30 Mar 2018 14:47 #1 by vlepetit
Hi,

How the critical path is calculate ?

Does we setup something particular to include task in critical path ?

Regards,
vlepetit
Last edit: 30 Mar 2018 14:47 by vlepetit.

Please Log in or Create an account to join the conversation.

More
30 Mar 2018 14:58 #2 by babynus
Once planning is calculate, a quick reverse planning is done, from end to start (taking only calculated duration of tasks), to determine latest start and end dates.
When planned dates are equal to latest dates, activity is on the critical path.

This means that if on task included in the critical path extends, whole projects extends of same duration.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
30 Mar 2018 15:26 - 30 Mar 2018 15:26 #3 by vlepetit
Ok,

but when there are none contiguous task in critical path, there is problem no ?
like when the planned end date of the first task is before the planned begin date of the next task, the critical path seem to not be display.

example in your projeqtor demo :
the task with wbs : 99.2.1 is the first task of an task chain. this task is none contiguous with the next task (wbs: 99.3.1) and it's not in critical path. but the task (wbs: 99.3.1) that is contiguous with the next step task, is in critical path.

It's normal ?

Regards
vlepetit
Last edit: 30 Mar 2018 15:26 by vlepetit.

Please Log in or Create an account to join the conversation.

More
30 Mar 2018 15:51 #4 by babynus
Yes, it's normal.

Concider that task 9.2.1 extends of 1 day : end date of project does not change.
So this task is not on critical path

Now, extend task 9.3.1 of 1 day : end date of project is delayd of same duration.
So this task is on critical path.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: vlepetit

Please Log in or Create an account to join the conversation.

More
30 Mar 2018 15:54 #5 by vlepetit
ok i understand !!

thank you !

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.034 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.